← Back to Permits & ServicesContent pending LGU confirmation
Bureau of Fire Protection
FSEC for Building Permit (BFP)
The Fire Safety Evaluation Clearance (FSEC) is issued by the Bureau of Fire Protection before a Building Permit is granted, confirming that building plans meet fire safety requirements under the Fire Code of the Philippines.
Requirements
- Three (3) complete sets of proposed plans covering: Architectural, Civil/Structural, Electrical, Mechanical, Plumbing, Electronics, Sanitary, and Fire Protection documents
- Fire Safety Compliance Report (FSCR), one (1) set, if necessary
- Cost estimate of the building, including labor cost, signed and sealed by the designer/contractor and duly notarized
- Fire Safety Clearance for Welding, Cutting, and other Hot Work Operations, if required
Good to Know
Normally required before the Building Permit itself is approved.